- ENI
- feasibility Study
- Sannazzaro de’ Burgondi (PV)
- 2020
The new convention center will be made of galvanized metal carpentry and painted at the service of two above ground levels, and it will be located inside ENI Refinery in Sannazzaro de’ Burgondi (PV).
The structural approach includes the following works:
- foundation in a.c. through an audience of size in plan of about 400×400 cm th. 70 cm, placed at an in-depth altitude of about 1.20m from the current campaign plan;
- n.24 main columns type HEB360 will be in metal carpentry;
- the metal carpentry of the roof will be made by main tubular Ø219.1x12mm circular shape, connected by tubular lattice beams Ø139.7x10mm and uprights/diagonals Ø88.9x6mm and other minor profiles.
With regard to the use and the consequent accidental overloads of the project, we referred to the current legislation and to the requirements provided by the Customer.