Cost Estimate to carry out engineering activity necessary to the installation of a new slurry filtration package at di Sannazzaro de’ Burgondi Plant.
Activity developed:
• Dismantling filtration package, equipment, lines, carpentry and existing foundations
• New structure foundations to locate filtration slurry skid
• New equipment foundations
• Transport and installation of new filtration package
• Transport and installation new equipment
• Existing pumps relocation
• Adaptation of underground networks (oil sewerage, fire-fighting network)
• Connection new package and equipment to existing piping